Some projects are best told in pictures. This one is our own development: a new building of four one-bedroom flats in Hampshire, which we started in 2024 and finished in 2025. Here is the whole story, from bare ground to the finished flats, told through the photos and time-lapse footage we took on site along the way.

The whole build in about 70 seconds.

1. Groundworks and foundations

Every build starts below ground. The site was cleared and set out, the foundations were dug and poured, and the drainage and service ducts were laid before anything could go up.

Groundworks under way for four new flats in Hampshire
Groundworks under way for four new flats in Hampshire

Next came the ground floor itself: a beam-and-block floor, with the water and service pipes brought up exactly where the plans needed them.

Beam-and-block ground floor with service pipes
Beam-and-block ground floor with service pipes
Ground floor slab complete
Ground floor slab complete

2. The ground-floor walls

With the floor in, the walls started to rise. The outer brick skin was built up alongside the inner blockwork, with the window and door openings formed as we went.

Ground-floor brick and block walls going up
Ground-floor brick and block walls going up
Ground-floor walls rising with window openings formed
Ground-floor walls rising with window openings formed

By the time the ground-floor walls were complete, you could walk through the building and see how the flats and their rooms would sit together.

Ground-floor walls complete
Ground-floor walls complete

3. The first floor

With scaffolding up, the first-floor joists went in and were decked over, giving a solid platform to build the upstairs from.

First-floor joists in place
First-floor joists in place
First-floor deck laid
First-floor deck laid

The first-floor walls then went up in the same way as the ground floor, taking the building to its full height.

First-floor walls going up
First-floor walls going up
Upper walls built to full height
Upper walls built to full height

4. The roof

The roof trusses were lifted into place and fixed, and the roof began to take shape. Once the roof is on, the building is weathertight and work can move inside whatever the weather.

Roof trusses fixed in place
Roof trusses fixed in place
The roof on, with scaffolding still up
The roof on, with scaffolding still up

5. Inside: floors and insulation

With the roof on and the building weathertight, the work moved inside. The ground floors were covered with a damp-proof membrane, then insulation boards were fitted edge to edge across every room before the floor finish went on top. You never see it once a home is finished, but it makes a real difference to how warm the flats are and how much they cost to heat.

Insulation boards going down over the damp-proof membrane
Insulation boards going down over the damp-proof membrane
Floor insulation laid and taped across a ground-floor flat
Floor insulation laid and taped across a ground-floor flat

Next, the partition walls and ceilings were framed and boarded, turning an open shell into separate rooms.

Partition walls framed and ceilings boarded
Partition walls framed and ceilings boarded

6. Kitchens and finishing

After the electrics, plumbing and plastering, the fitted kitchens went in, and wood-effect flooring was laid through the living spaces.

A fitted kitchen going in
A fitted kitchen going in
Kitchen fitted, with the new flooring down
Kitchen fitted, with the new flooring down

7. Finished

By spring 2025 the building was complete: four one-bedroom flats in facing brick with stone-coloured window heads and sills, new windows and doors, and a block-paved parking area at the front. A date stone above the front doors marks the year we built it.

The finished building, with our vans outside
The finished building, with our vans outside
Front doors to two of the four flats
Front doors to two of the four flats
Paved outside space at the back
Paved outside space at the back

If you would like to know more about each stage of a new build, read building a new home: from plot to handover.